|
Abstract
LNG receiving or import terminals are not a new phenomenon, with over 40 in
existence worldwide, the oldest being more than 30 years old. At present,
there is renewed interest in LNG receiving terminals outside Japan, due to the
increased demand for clean burning energy and an abundance of natural gas
worldwide. Currently, there are at least 50 proposed new receiving terminals
in various stages worldwide; more than 35 potential projects have been
identified for the North American market alone. This paper will address the
key drivers governing LNG receiving facility design and will then examine key
design issues for each of the main elements os such terminals. This paper
primarily addresses the issues surrounding onshore terminals, but also in
specific areas highlights the differences between an onshore and offshore
facility.
Introduction
The cost for an LNG import facility varies, but can be US $ 400 million or
more, and is dependent upon many factors. Nonetheless, it is a small component
of the entire LNG value chain shown in Figure 1.
The major elements of an LNG import terminal and the range of costs for a 3
million tones per annum (MTPA) facility are shown in Figure 2.
The schedule for completion of an LNG terminal is approximately 48 months from
the start of front-end engineering design (FEED), or 33-36 months from EPC
contract award. The critical path will be through the LNG tanks, which will
take 32-34 months to complete. In addition, permitting can add significantly
to the total project duration.
LNG Receiving Facility Design
The key drivers that govern the design and cost of an LNG receiving facility
are:
-
Location
-
Regulatory requirements and design codes to be used * Site characteristics
(soil conditions, earthquake potential, marine bathymetry, environmental
conditions)
-
Availability of local infrastructure including labor
-
Capacity of the facility
-
Operating issues: reliability and availability required for the facility
-
Source(s) of LNG supply and characteristics
-
Gas send-out characteristics
-
Safety and security considerations
-
Owner's risk requirements
|